Quick Answer
Under a TREC new home contract, no, the price is fixed unless both parties amend it in writing. But most Texas production builders use their own contracts, and those can include material escalation or cancellation clauses that allow price changes. The answer is in the four corners of the contract you sign, so read the price, escalation, and termination sections before you sign.
Texas does not have a statute that flatly bars a builder from raising the price after signing, so the protection comes from the contract itself. The TREC new home contracts are fixed-price forms with no escalation clause, but builders are allowed to use their own attorney-drafted contracts, and the large production builders typically do.
The builder-drafted contracts commonly include material price escalation language, which lets the builder pass through cost increases beyond a certain trigger, and cancellation or convenience clauses that can let the builder walk away. None of that makes a builder untrustworthy, it makes the contract the document that decided your risk, which is why I read the escalation and termination sections with every new build buyer before they sign, not after.
TREC forms versus builder contracts
TREC publishes two new home contract forms, one for incomplete construction and one for completed construction, and both set a fixed sales price with no unilateral price adjustment. Builders, however, are not required to use TREC forms when they sell their own homes, and most large builders use their own contracts, which are where price changes get written in.
Ask directly which form the builder uses. If it is a TREC form, the price is fixed absent a written amendment. If it is the builder's form, the escalation and termination language is the fine print that decides the risk.
The clauses that change the price
Material escalation clauses pass through cost increases when materials rise beyond a set trigger, and cancellation or convenience clauses can let the builder terminate or renegotiate. Read those sections line by line, and if you do not want the risk, negotiate a hard cap on any escalation and a written commitment that the price holds.
Because this is contract law, not sales talk, have the builder's contract reviewed if the escalation language is anything beyond plain English. The cost of that review is nothing next to a five-figure price increase.
How to protect the price you were quoted
Get the price commitment in writing before you pay any deposit, read the escalation and termination clauses in the actual contract, and ask for a written cap on any potential increase. Confirm what happens to your deposit if the builder terminates, because that clause decides whether the builder walks with your money.
Bring any pre-sale price sheet and the final contract to one meeting and compare them line by line. That fifteen-minute read is the difference between the home you agreed to and the home that arrives with a new price.
Ask Patrick about the builder contract
Get the escalation and termination clauses read before you sign the new build contract.